Do you work internationally?

Yes, absolutely. Although our headquarters and heart are in the Netherlands, our services reach worldwide. Our engineers regularly fly out to [...]

Read more
20 December 2025

Can you find the cause of a faulty frequency converter?

Yes, this is a common problem. Often the cause is voltage dips or harmonic contamination affecting the input stage of the [...]

Read more
20 December 2025

My installation complies with NEN 3140, why do I still have faults?

NEN 3140 is a safety inspection focusing on touch hazard and fire safety at a basic level. It does not look at the quality of the [...]

Read more
20 December 2025

Do you also provide a solution after measurement?

Absolutely. We are not an inspection agency that just diagnoses a problem. We recommend concrete solutions, such as harmonic filters or capacitor banks, and [...]

Read more
20 December 2025

What is the difference between Power Quality and EMC?

Power Quality deals with the quality of the power supply up to frequencies of about 2.5 kHz (harmonics, dips). EMC (electromagnetic compatibility) [...]

Read more
20 December 2025

Do you also measure magnetic radiation?

Yes, we carry out EMF (Electromagnetic Fields) measurements. We often do this in office buildings, hospitals or near heavy transformers to [...]

Read more
20 December 2025

Can I rent a meter and send the data myself?

This is possible, but we often advise against it for complex problems. Meter placement (correct phase sequence, type of current clamps) [...]

Read more
20 December 2025

What does a grid analysis cost?

Costs depend on the duration, number of measurement points and complexity of the analysis. Contact us for [...]

Read more
20 December 2025

Should the power be off during meter installation?

In most cases, they don't. Our engineers are trained to work safely in the vicinity of live parts and [...]

Read more
20 December 2025

How long does a Power Quality measurement take?

For a complete analysis in accordance with standard EN 50160, we recommend a minimum of one week (7 days). This ensures that [...]

Read more