Standards and grid connection
Grid codes / connection conditions
Grid codes, laid down in the Netherlands in the Electricity Network Code, are the technical rules for everyone connected to the electricity grid. If your installation does not comply, you will face fines, a refusal to approve an extension or internal faults caused by contamination. HyTEPS carries out measurements at the transfer point and simulates in advance whether an extension will remain within the requirements.
This article comprises 10 sections
- In brief
- What are grid codes and connection conditions?
- What it costs if you do not comply
- How to recognise that you may not be compliant
- Where the interference comes from
- Example: an expansion project that stalled
- What you can do about it
- Compliance checklist
- When should you call in an engineer?
- Frequently asked questions
In brief
- What
- Grid codes are the technical requirements that your installation must meet in order to be permitted to connect to the electricity grid.
- Why
- It is not just about what you consume, but increasingly about what you generate or feed back into the grid: harmonics and reactive power.
- Consequence
- Fines, forced disconnection by the distribution system operator (DSO) or transmission system operator (TSO), or refusal of new connections.
- Approach
- A measurement at the point of connection (PCC) provides a definitive answer. Compliance can be achieved through engineering and hardware such as active filters.
What are grid codes and connection conditions?
They set out the rights and obligations between the network operator (DSO or TSO) and you as a consumer or producer. Think of it as similar to the discharge requirements for waste water: you are permitted to discharge into the sewer system, provided you do not discharge anything that could damage the system. In an electrical installation, this concerns harmonic distortion, voltage fluctuations and reactive current.
The requirements apply at the Point of Common Coupling (PCC), the transfer point: the boundary between the public grid and your installation.
The grid operator
- Guarantees a specific level of voltage quality, often based on EN 50160.
You, as the customer
- Ensures that the electricity consumed and the energy fed back into the grid remain within specified limits, so that you do not disrupt other grid users.
Voltage is not the same as current. EN50160 describes the voltage you receive. The connection conditions often relate to the power quality you generate or feed back into the grid. You are responsible for your own power quality issues.
What it costs if you do not comply
The energy transition is putting pressure on the grid, and grid operators are enforcing stricter standards. Whereas in the past it was mainly heavy industry that faced strict requirements, this now applies to virtually every large-scale consumer, particularly those with heavy power electronics or on-site generation: industry, data centres, hospitals and maritime applications with shore power.
- Financial penalties. If you exceed the limits for reactive power (cos phi) or peak load, you will face fines or higher transmission charges on your energy bill.
- A rejected expansion. If you wish to install solar panels or a new production line, the grid operator may refuse permission unless you can demonstrate that you remain within the emission limits.
- Forced disconnection. If your installation threatens grid stability – for example, due to severe harmonic distortion or flicker – the grid operator is entitled to disconnect you.
- Damage to in-house equipment. Overheated transformers, control system failures and accelerated wear and tear.
How to recognise that you may not be compliant
- Penalties on the energy bill: Terms such as reactive power penalties, or surcharges for exceeding the contracted transmission capacity.
- A hot or humming transformer, even though the load in kW appears to be well below the maximum. This often indicates harmonic distortion.
- Problems during switchover: When a standby generator or UPS is switched on, some equipment fails because it is more sensitive to contamination than the mains supply.
- Flickering lighting: Lamps flicker when heavy machinery is switched on. This often indicates that the permitted limits for voltage dips have been exceeded.
- Communication faults: Measurementand control technology produces unexplained error messages, often caused by high-frequency interference feeding back into the grid.
Where the interference comes from
Rarely caused by a single device, but usually by the cumulative effect. In the past, loads were linear, such as incandescent light bulbs and directly connected motors. Nowadays, they are increasingly non-linear.
- Power electronics. Variable frequency drives (VFDs), rectifiers and inverters chop the current into pieces. This results in harmonic distortion.
- Renewable energy generation (PV and wind). If incorrectly designed or configured, solar panel inverters can cause the voltage to rise and result in undesirable resonances with the grid.
- LED lighting and EV chargers. Energy-efficient, but often with a low power factor, and they generate harmonics.
- Long cables. Long cable runs, whether in industrial settings or offshore, act as capacitors and generate excess capacitive reactive power. Grid operators monitor this very closely.
Example: an expansion project that stalled
A manufacturing company in the metal industry wanted to expand by adding two welding robots and a large press. To increase the connection capacity, the grid operator required proof that the new setup would not cause unacceptable grid pollution (interference).
- Problem. The installation was already operating at the limit for harmonic distortion (THDi). The robots would exceed the limits set by the Grid Code.
- Analysis. HyTEPS carried out a baseline measurement and simulated the new machines. The 5th and 7th harmonics, in particular, were found to exceed the limit values.
- Solution. An active harmonic filter (AHF), which continuously measures harmonic distortion and injects a counter-current.
- Result. Disturbances at the transfer point fell well within the standards, and the grid operator approved the expansion.
What you can do about it
Compliance with grid codes is an ongoing process, not a one-off action. You tackle it on three levels.
-
Rapid diagnosis
- Check your bill. Are you paying for reactive power?
- Assessment. What major power electronics equipment has been added recently, such as EV chargers, heat pumps or variable frequency drives?
-
Structural engineering
- A power quality measurement at the PCC. A standard energy meter is insufficient. You need equipment that records harmonics, transients and imbalance in accordance with IEC 61000-4-30 Class A.
- Simulation. With new builds, it is not possible to carry out measurements. A simulation study predicts whether the design complies with the grid code.
-
Hardware troubleshooting
- Active harmonic filter. Filters harmonics, compensates for reactive power and can eliminate imbalance.
- Capacitor banks. The traditional solution for reactive power compensation. Beware of resonance with harmonics: always use detuned banks in a contaminated environment.
- Hybrid. A combination of passive and active filtering, offering cost-effective solutions.
Read more about the active harmonic filter and the capacitor bank.
Our engineers carry out measurements at the transfer point and simulate whether the new situation remains within the grid operator’s requirements.
Compliance checklist
- Insight
Is there a current single-line diagram and a power balance?
- Data
Is there a recent power quality measurement covering at least one week at the PCC?
- Analysis
Have the results been checked against the Grid Code and the terms of the contract with the grid operator?
- Solution
Are filters or compensation required?
- Verification
Were measurements taken again after installation to demonstrate proper operation?
When should you call in an engineer?
In the following situations, it is advisable to consult a HyTEPS engineer:
- You have received a warning or a fine from the grid operator.
- You are planning a major expansion: a new build, a solar park or the electrification of your vehicle fleet.
- Are you unsure whether your installation meets the legal requirements, for example for insurance purposes or an audit?
- You are experiencing unexplained failures of sensitive equipment.
We analyse your installation using measurements and simulations to tackle the root cause effectively.
Frequently asked questions
Do solar panels and LED lighting affect my power quality?
Yes, significantly. Solar panel inverters and LED lighting drivers are non-linear loads that generate harmonics and, in some cases, supraharmonics. This can interfere with other equipment or overload the neutral conductor. You should therefore have the power quality checked during any renovation or sustainability upgrade.
Will my installation comply if I stay within the NEN-EN 50160 standard?
Not necessarily. The standard sets out the minimum requirements at the grid operator’s transfer point. Modern equipment may be more sensitive and could malfunction, even if the voltage falls within the standard. We therefore assess the compatibility between your power supply and your load.
Is installing an Active Harmonic Filter always the solution?
No. A filter is a powerful tool, but not a miracle cure. Sometimes the solution lies in adjusting the transformer settings, redistributing loads or modifying the cabling. That is why HyTEPS recommends an analysis and simulation first, before advising on hardware.
How long does a typical Power Quality survey take?
To obtain a reliable picture, we usually carry out measurements over a period of at least one to two weeks, so that a full operating cycle, including weekends and peak loads, is recorded. In the event of acute faults, we can also carry out short-term measurements or utilise continuous waveform recording.
What is the next step after an analysis?
You will receive a report containing conclusions in plain language alongside the technical details. Where necessary, we simulate the solutions so that you know in advance how a particular measure will perform. We then oversee the implementation and verify the result with a follow-up measurement.
Read more
Have your installation assessed by an engineer
You’ll receive a reply within one working day. Your first consultation will be with an engineer.