Mauser: Up to 500 A extra capacity

Mauser in Oosterhout was paying monthly fines for reactive power and lacked sufficient power capacity for new machinery. Following measurements, HyTEPS installed filters at transformer level. This provided up to 500 A of additional capacity.

Client
Mauser Packaging Solutions, Oosterhout
What happened
Reactive current penalties and insufficient capacity
What we did
Measurements on 13 feeders, filters and meters
Result
Up to 500 A extra capacity

The background

The Mauser Packaging Solutions production site in Oosterhout houses six transformers and a machine park comprising 20 blow moulding machines and 19 injection moulding machines. Reactive current resulted in monthly fines from the energy supplier. Harmonic distortion from certain controllers even spread to other main distribution boards.

Mauser wanted two things: to put an end to the fines and to free up power for new machinery, without having to go through a lengthy process to upgrade to a higher-capacity connection.

The diagnosis

Our engineers carried out a comprehensive power quality measurement on 13 outgoing feeders, using continuous waveform recording. On a number of feeders, the harmonic power was found to be even higher than the reactive power. This indicates a heavy load on components and a greater risk of faults.

This provided a comprehensive overview of the entire installation, including the impact of harmonics on the transformers. These measurements formed the basis for the improvement plan.

The solution

HyTEPS installed harmonic filters at transformer level, so that the pollution is tackled at source. The filters neutralise harmonics and improve the power factor. In addition, power quality meters have been installed to continuously monitor the installation.

The result

Up to 500 A extra capacity

Reactive current penalties are a thing of the past, and the physical strain on the installation is reduced. Mauser can utilise up to 500 amps of additional capacity within the existing infrastructure.

Using the meters, Mauser can monitor consumption right down to the machine level. This enables the company to save energy by optimising the sizing of its processes.

Used in this project

HyTEPS immediately understood what we needed. They not only removed reactive power, but also freed up extra power, and made our power network healthier. We are now looking at how we can potentially release even more power by smart sizing.

Reinier GoordenInstallation manager, project engineer and power coordinator