The Invisible Threat of Flame Arcs in Large-scale Energy Storage

The energy transition calls for innovative solutions, such as iwell's impressive 'MegaCube' at Eneco's site in Utrecht Lage Weide. With a capacity of 14,000 kWh, this system plays a key role in balancing the power grid and reducing gas consumption. However, such huge capacities carry significant, often invisible risks. The integration of six containers with battery systems and three transformers connected directly to medium voltage creates a complex electrical infrastructure. The challenge for iwell was clear: how do we ensure the absolute safety of personnel and equipment in an environment where huge amounts of energy can be released in milliseconds?

The need for security was reinforced by the stringent requirements of supplier Tesla. Before any maintenance work was allowed to take place, a detailed arc calculation was required. This is not a bureaucratic formality, but an essential safety measure to prevent fatal injuries caused by arc flash. Uncertainty about the exact energy levels in the event of a potential short circuit was a roadblock to safe management. As Technical Project Manager Kolijn Venema of iwell points out:

"You do have a kind of moral obligation to carry that out, I think, for the personal safety of people working around and on the installations."

Working with HyTEPS was very pleasant, both with Christan and the executive engineers. They ask thorough questions to understand our question and need exactly. I personally also liked that HyTEPS employs people from all over the world, including from an ideological background.

Kolijn Venema Technical Project Manager Full story
Monitoring Engineer

Diagnostics and Modelling: The Truth Behind Security Settings

Based on the technical documents, HyTEPS built a model to simulate the behaviour of the protection systems in the installation. The aim was to calculate exactly how much energy is released during a short circuit and whether this could lead to personal injury. This simulation showed that the existing settings of the protection circuit breakers and policies needed to be adjusted to prevent an excessive amount of electrical energy from spilling over to a person.

Christan van Dorst, Manager of Technical Engineering, noted that the calculated arc energy was too high due to sub-optimal settings. "In the case of an arc, longer delays associated with the short-circuit tripping time can lead to dangerous levels of arc energy being released from a distribution box," he explained. HyTEPS then made a concrete proposal to reduce this energy.

Safety Without Compromise: Selectivity and Protection in Balance

The advised proposals were implemented immediately: the new breaker 'trip' times have been reduced to 0.12s and 0.08s, where previously they were 0.48s and 0.27s. These reductions of 75% and 70% ensure shorter trip times, reducing energy levels during an arc while maintaining coordination between protective devices. This makes the cabinets safer and, in the event of an incident, the right device is always switched off correctly.

In addition to the technical modifications, arc labels have been installed and the Personal Protective Equipment (PPE) required per cabinet has been defined for safe working. Kolijn Venema of iwell concludes, "HyTEPS definitely helped us improve the security concept of the installation. It was surprising in a way, because we had assumed that security settings would ensure good safety for everyone. But so according to the arc study, that turned out to be not enough".

Engineer

Security in every kilowatt

Flame arcs are a real risk for any industrial plant. Leave nothing to chance. Our specialists analyse your risks and guarantee a safe working environment through compliance with the strictest standards.

HyTEPS

Beemdstraat 3

5653 MA Eindhoven

Similar projects

550 Amp released power: from capacity problem to growth space

Nijsen was struggling with high costs and lack of capacity due to reactive power. Our active capacitor banks eliminated the penalties and immediately created 550 amps of extra space on the transformers.

500 amp extra capacity and complete elimination of blind current penalties at Mauser

Through targeted measurements and active filtering, HyTEPS eliminated grid contamination and blind current penalties at Mauser Packaging Solutions . This immediately provided 500 amps of extra capacity, allowing production to scale up safely without investing in a heavier grid connection .

Full operational reliability through elimination of grid contamination at Sappi Maastricht

Sappi Maastricht eliminated costly production downtime by targeting harmful harmonics with a Power Quality diagnosis and active filtering. This investment fully restored operational reliability and paid for itself within a year due to the guaranteed continuity.

Grid analysis at PLB Group prevents unnecessary battery investment

An independent Power Quality measurement at PLB Group exposed unused spare capacity. Through targeted optimisations, we avoided the purchase of an expensive battery storage system. This provides the customer with enormous cost savings, while maintaining security in every kilowatt.

Maximum operational reliability for Amphia: 100% grip on Power Quality

Our engineers analysed Power Quality with continuous waveform recording to ensure maximum safety. Thanks to continuous monitoring, all risks are now under control and care continuity is guaranteed.

No room for error: how Zentrys guarantees 24/7 continuity

HyTEPS ensures the operational reliability of Zentrys through targeted arc scanning and selectivity testing. With digital simulations, we eliminate invisible risks for maximum continuity and a safe working environment.

Real-time Power Quality insight secures production of 290,000 tonnes of zinc

By tackling unexplained outages with high-end monitoring, HyTEPS ensured continuity at Nyrstar. Real-time insight into Power Quality now prevents unnecessary downtime.

Continuity in passenger flows through EMC control

Harmonic contamination threatened the continuity of Schiphol's security lanes. HyTEPS analysed the risks and installed seven active filters to restore grid quality. The result is a stable installation and guaranteed operational security for millions of passengers.

From unexplained outages to maximum operational reliability: Power Quality at Vencomatic Group

Conservation at Vencomatic inadvertently led to harmonic contamination and failure of critical equipment. After a proactive Power Quality measurement, our engineers implemented Active Harmonic Filters, which successfully stabilised the plant and ensured operational reliability.

1.75 MW of power released and direct cost reduction at SNB

Despite own generation, SNB was struggling with high costs due to reactive power. HyTEPS optimised the installation with capacitor banks. The result: 1.75MW less grid load and a payback time within one year.

Direct cost savings and extra capacity for Van Munster Recyclers

Van Munster Recyclers eliminated the reactive power penalty and immediately created additional capacity with a HyTEPS capacitor bank. Thanks to the immediate cost savings, this solution paid for itself within one year.

Structural cost reduction through elimination of reactive power penalties at VDL Parree

By deploying a 300 kVA capacitor bank, HyTEPS stopped monthly reactive power penalties at VDL Parree. This intervention increased efficiency and created additional capacity immediately, so the investment paid for itself within a year.

Extra production capacity through Cos Phi optimisation at Naber Plastics

HyTEPS increased installation capacity at Naber Plastics by targeting reactive power. With a 400kVAr capacitor bank, our engineers immediately created space for additional machinery. This results in optimum power utilisation and maximum operational reliability.

Sustainable expansion without grid reinforcement at Clondalkin Flexible Packaging

HyTEPS ensures continuity at Clondalkin with a system that combines energy insight with automatic HACCP recording. This eliminates risky manual checks and maximises operational reliability.

75% Faster shutdown times for safe battery storage at iwell

For iwell's battery system, HyTEPS conducted an Arc Flash Compliance study to ensure electrical safety. The new settings reduced shutdown times by 75%, reducing dangerous arc flash energy to safe levels.

Maximum operational reliability for offshore giant: ground loops eliminated

HyTEPS eliminated years of cable insulation damage on the Bumblebee due to a hidden ground loop in the complex offshore installation through a focused Power Quality. This proactive approach restores operational continuity and provides Allseas with the maximum reliability their operation requires.

National security of supply secured with large-scale Power Quality monitoring

HyTEPS continuously analyses and validates Power Quality data from the entire Dutch power grid. Our customised software transforms this complex data stream into reliable control information for optimal security of supply.

100% operational reliability for taxiway lighting at Schiphol Airport

HyTEPS identified the risks to the taxiway lighting at Schiphol Airport through accurate measurements. With the subsequent solution, the continuity and safety of this critical installation is fully guaranteed.

Optimisation of grid capacity and operational reliability at OVET B.V.

Grid congestion and complex Power Quality issues threatened to stall OVET B.V.'s expansion plans. HyTEPS implemented an advanced monitoring system that provides exact insight into consumption and peaks. This allows OVET to safely expand and make maximum use of existing capacity without the risk of outages.

Communication stability ensured by elimination of EMI at Schiphol Airport

HyTEPS eliminated electromagnetic interference in the Schiphol T2000 network after an integral EMC study. This approach restored system integrity and guaranteed uninterrupted communication for emergency services.

100% care continuity through optimal Power Quality at Rivierenland Hospital

Hospital Rivierenland ensures safe care by working with HyTEPS to eliminate harmonic contamination in the installation. The deployment of Active Harmonic Filters now guarantees optimum Power Quality and maximum operational reliability.

Preventing unplanned downtime by eliminating harmonic pollution at Nyrstar

HyTEPS eliminated high-risk harmonic contamination at Nyrstar. Our specialist measurements provided an exact diagnosis and a guaranteed stable production environment.

5MW plant safely expanded without grid congestion risk

To prevent downtime at the new 5MW plant, HyTEPS preventively implemented two Active Harmonic Filters. This assures ARN Recycling of a stable energy network and maximum business continuity.

Maximum grid capacity through targeted reactive power compensation at Xella

HyTEPS restored installation capacity at Xella by targeting reactive power with capacitor banks. The solution offers Xella an immediate cost reduction and sustainable security in every kilowatt.

4MW solar panels integrated without grid pollution at KLM

HyTEPS integrated 4 MW of solar panels at KLM Schiphol without risk. By eliminating grid pollution with Active Harmonic Filters, we ensure maximum operational reliability and a stable installation in Hangar 14.

Optimal operational reliability through data-driven energy monitoring

HyTEPS implemented an advanced monitoring system that gives CurTec real-time grip on energy consumption and Power Quality. This data-driven solution prevents blind power penalties and ensures a stable, climate-neutral future.

Safe innovation: Arc calculation for the world's fastest charging battery

Our engineers performed specialist arc simulations to ensure the safety of InMotion's unique battery pack. Thanks to this concrete analysis, the team is now working on ultra-fast charging technology with the right protective equipment and complete certainty.

Production outages eliminated by stable Power Quality at Mannesmann

HyTEPS solved the failure of air compressors at Mannesmann by immediately eliminating harmful harmonic contamination. With active filtering and continuous monitoring, precision tube production is now fully stabilised.

Fault-free LED transition for De Kuip stadium

In an environment where tens of thousands of spectators count on continuity, downtime is not an option. HyTEPS secures Power Quality at Stadion Feijenoord, so that the transition to LED lighting leads directly to guaranteed performance without invisible risks.

Halving harmonic contamination increases operational reliability at Thialf

Thialf was struggling with unexplained failure of critical variable speed drives. HyTEPS implemented Active Harmonic Filters, which successfully reduced the harmonic pollution (THDu) present to below 4%. Supplemented by permanent monitoring, this now ensures an extremely stable and reliable installation.

Rijkswaterstaat ensures tunnel safety with 40% spare capacity

HyTEPS eliminates harmonic pollution in the Ruhr Tunnel by implementing four active filters. Thanks to 40% spare capacity, technical safety for Rijkswaterstaat is guaranteed under all circumstances.