Feijenoord Stadium: LED conversion assessed for grid risks

Feijenoord Stadium is switching to LED lighting in the floodlight masts and along the roof edge. HyTEPS measured the installation during a match, simulated the new luminaires and verified the results with a validation measurement.

Client
Feijenoord Stadium (De Kuip)
What happened
Switch to LED lighting
What we did
Baseline measurement, simulation and validation measurement
Result
LED conversion assessed for grid risks

The background

Feijenoord Stadium is switching to LED lighting in the four floodlight masts and along the roof edge. LED luminaires last longer and use less energy, but they also present certain challenges during installation.

Large numbers of LED drivers can cause harmonic distortion, high inrush currents and an unforeseen load on the neutral conductor. As well as football matches, De Kuip also hosts concerts and conferences. Any outage during a live broadcast would have significant financial consequences.

The diagnosis

Our engineers carried out a baseline measurement during a match, as the installation only reveals how power quality behaves under full load. Everything was recorded using continuous waveform recording. This data formed the basis for a simulation model.

In this model, the characteristics of the new luminaires have been analysed, such as harmonic current and inrush currents. EMC and supraharmonics have also been investigated to ensure that protective devices do not trip unnecessarily.

The solution

Based on the analysis, the installation was modified. A key aspect was reducing the voltage, in consultation with the network operator, to ensure it met the requirements of the new luminaires. The installation was monitored throughout the works.

The result

The installation is performing as designed

The final validation measurement shows that the installation is performing as designed. Feijenoord Stadium now has a validated model and a final report. The risk of faults is low.