At CurTec International, continuity is the standard in a 24/5 production environment. Our engineers realised an advanced monitoring system that links energy consumption directly to machine performance. This provides the technical staff with the peace of mind and certainty that every kilowatt is used optimally.
In CurTec's high-end plastic packaging industry, injection moulding and blowing machines run continuously. Without detailed insight into consumption per machine, optimisation opportunities remained unexploited and invisible risks such as reactive power penalties and unplanned downtime loomed. The challenge was clear: move from intuitive decision-making to a factual, technically-based strategy.
The fear of production stops and the growing pressure to achieve a climate-neutral value chain called for a partner that takes responsibility. "You can't optimise what you don't measure," a reality that at CurTec led to the need for a clear diagnosis of the entire plant.

HyTEPS uses a strict methodology to ensure the technical integrity of the installation. We installed five Ethernet-connected BFM-II Power Quality meters in the crucial main distribution cabinets. These units monitor up to 27 three-phase load points, using continuous waveform recording to capture any anomaly in the grid.
Our engineers performed accurate calibration of voltage, current and phase parameters. Through this in-depth analysis, we translate complex Power Quality data into directly usable insights for technical staff. This proves our role as an expert partner; we not only identify the symptoms, but model the full impact on operational reliability.
We implemented the ExpertPower platform, giving CurTec's engineers real-time access to critical data. Our proactive approach enables CurTec to link energy consumption directly to output per product. This allows the team to immediately identify the most efficient machines and resolve blind power issues before they lead to penalties or damage.
The result is a stable installation where decisions rest on facts. Active monitoring eliminated uncertainty about the cause of inefficiency. We minimised risks during implementation, giving CurTec the certainty it needed.

A reliable installation starts with a clear diagnosis. HyTEPS offers the technical expertise and decisiveness to take your Power Quality to the highest level. We take responsibility for your electrical infrastructure so that you can focus on your core business.
HyTEPS
Beemdstraat 3
5653 MA Eindhoven
Nijsen was struggling with high costs and lack of capacity due to reactive power. Our active capacitor banks eliminated the penalties and immediately created 550 amps of extra space on the transformers.
To prevent downtime at the new 5MW plant, HyTEPS preventively implemented two Active Harmonic Filters. This assures ARN Recycling of a stable energy network and maximum business continuity.
Despite own generation, SNB was struggling with high costs due to reactive power. HyTEPS optimised the installation with capacitor banks. The result: 1.75MW less grid load and a payback time within one year.
By tackling unexplained outages with high-end monitoring, HyTEPS ensured continuity at Nyrstar. Real-time insight into Power Quality now prevents unnecessary downtime.
Harmonic contamination threatened the continuity of Schiphol's security lanes. HyTEPS analysed the risks and installed seven active filters to restore grid quality. The result is a stable installation and guaranteed operational security for millions of passengers.
HyTEPS restored installation capacity at Xella by targeting reactive power with capacitor banks. The solution offers Xella an immediate cost reduction and sustainable security in every kilowatt.
HyTEPS increased installation capacity at Naber Plastics by targeting reactive power. With a 400kVAr capacitor bank, our engineers immediately created space for additional machinery. This results in optimum power utilisation and maximum operational reliability.
HyTEPS ensures the operational reliability of Zentrys through targeted arc scanning and selectivity testing. With digital simulations, we eliminate invisible risks for maximum continuity and a safe working environment.
HyTEPS eliminated years of cable insulation damage on the Bumblebee due to a hidden ground loop in the complex offshore installation through a focused Power Quality. This proactive approach restores operational continuity and provides Allseas with the maximum reliability their operation requires.
Sappi Maastricht eliminated costly production downtime by targeting harmful harmonics with a Power Quality diagnosis and active filtering. This investment fully restored operational reliability and paid for itself within a year due to the guaranteed continuity.
In an environment where tens of thousands of spectators count on continuity, downtime is not an option. HyTEPS secures Power Quality at Stadion Feijenoord, so that the transition to LED lighting leads directly to guaranteed performance without invisible risks.
Through targeted measurements and active filtering, HyTEPS eliminated grid contamination and blind current penalties at Mauser Packaging Solutions . This immediately provided 500 amps of extra capacity, allowing production to scale up safely without investing in a heavier grid connection .
HyTEPS integrated 4 MW of solar panels at KLM Schiphol without risk. By eliminating grid pollution with Active Harmonic Filters, we ensure maximum operational reliability and a stable installation in Hangar 14.
By deploying a 300 kVA capacitor bank, HyTEPS stopped monthly reactive power penalties at VDL Parree. This intervention increased efficiency and created additional capacity immediately, so the investment paid for itself within a year.
Van Munster Recyclers eliminated the reactive power penalty and immediately created additional capacity with a HyTEPS capacitor bank. Thanks to the immediate cost savings, this solution paid for itself within one year.
HyTEPS ensures continuity at Clondalkin with a system that combines energy insight with automatic HACCP recording. This eliminates risky manual checks and maximises operational reliability.
Hospital Rivierenland ensures safe care by working with HyTEPS to eliminate harmonic contamination in the installation. The deployment of Active Harmonic Filters now guarantees optimum Power Quality and maximum operational reliability.
HyTEPS implemented an advanced monitoring system that gives CurTec real-time grip on energy consumption and Power Quality. This data-driven solution prevents blind power penalties and ensures a stable, climate-neutral future.
HyTEPS identified the risks to the taxiway lighting at Schiphol Airport through accurate measurements. With the subsequent solution, the continuity and safety of this critical installation is fully guaranteed.
Our engineers performed specialist arc simulations to ensure the safety of InMotion's unique battery pack. Thanks to this concrete analysis, the team is now working on ultra-fast charging technology with the right protective equipment and complete certainty.
HyTEPS eliminates harmonic pollution in the Ruhr Tunnel by implementing four active filters. Thanks to 40% spare capacity, technical safety for Rijkswaterstaat is guaranteed under all circumstances.
Our engineers analysed Power Quality with continuous waveform recording to ensure maximum safety. Thanks to continuous monitoring, all risks are now under control and care continuity is guaranteed.
HyTEPS continuously analyses and validates Power Quality data from the entire Dutch power grid. Our customised software transforms this complex data stream into reliable control information for optimal security of supply.
HyTEPS eliminated electromagnetic interference in the Schiphol T2000 network after an integral EMC study. This approach restored system integrity and guaranteed uninterrupted communication for emergency services.
HyTEPS eliminated high-risk harmonic contamination at Nyrstar. Our specialist measurements provided an exact diagnosis and a guaranteed stable production environment.
HyTEPS solved the failure of air compressors at Mannesmann by immediately eliminating harmful harmonic contamination. With active filtering and continuous monitoring, precision tube production is now fully stabilised.
For iwell's battery system, HyTEPS conducted an Arc Flash Compliance study to ensure electrical safety. The new settings reduced shutdown times by 75%, reducing dangerous arc flash energy to safe levels.